May 10, 2016 – Park Closure Countdown

0 days left – Construction begins at Alamo Square.

Some nearby alternate dog play areas and children’s playgrounds can be found below.


Project Scope

Irrigation Replacement

  • Replace antiquated irrigation system
  • Install “smart” controllers
  • Replace quick coupler lines
  • Install booster pump
  • 37% water savings, or 3,260,000 gallons

Wheelchair-Accessible Restroom

  • The curving walls of the restroom mimics the nearby playground


  • New lawn in the dog play area and open areas of the park
  • Native no-mow grasses at the park perimeter along Fulton and Scott streets
  • Understory shrub plantings at park entrances and interior installed in phases
  • 40+ new tree plantings installed in phases

Project Schedule

  • Construction will begin early May 2016
  • 10/5/16 Update: Open to the public March 2017 (orig. Fall / Winter 2016)

Construction Budget

  • Total Construction Cost $2,434,100

More info: