Hayes Sewer, Water, and Paving Project Update 5/1/2017

On Tuesday April 18, 2017, the contractor began sewer main replacement work on Hayes Street between Laguna and Buchanan.

Week of May 8, 2017

–  Crews are scheduled to commence water main replacement work at the Haight & Scott streets intersection.

– The contractor will continue sewer main replacement work on Hayes Street between Laguna and Buchanan streets. The sewer work is tentatively scheduled to wrap up this week on the block. Crews will then commence sewer main replacement work on Hayes between Buchanan and Webster streets.

http://www.sfpublicworks.org/haight-hayes

 