DPW Sewer Line Update 9/23/2016
This week
Crews continued sewer lateral work on Haight Street between Fillmore and Steiner streets. The lateral replacement work on this block should be complete next week.
Also this week, the contractor continued sewer main replacement work on Hayes Street between Scott and Divisadero streets. The mainline work on this block is expected to take another 2-3 weeks to complete. Once work on the main line is complete, crews will schedule sewer lateral replacement on the block.
Week of September 26, 2016
Crews will also continue sewer lateral replacement work on Haight Street between Fillmore and Steiner streets. The contractor will then continue localized sewer lateral replacement work on Haight Street. The “no parking” barricades will be placed at any locations where lateral work is to be performed. This work won’t impact sewer service.
Sewer main replacement will continue on Hayes Street between Scott and Divisadero.
*** Please Note: The schedule is subject to change due to rain, equipment breakdown, and/or unforeseen field conditions. Please see the posted “no parking” barricades for exact parking restrictions. Parking restrictions may vary per block. ***
Contact:
Alex M. Murillo
Public Affairs Officer
Office of Communications & Public Affairs | San Francisco Public Works | City and County of San Francisco
30 Van Ness Ave., 5th Floor | San Francisco, CA 94102 | W (415) 558-5296 | sfpublicworks.org ·twitter.com/sfpublicworks
For additional information on the project and to sign up for email updates, please visit www.sfpublicworks.org/haight-hayes.
Leave a Reply
Want to join the discussion?Feel free to contribute!