DPW December 2017 Update

An update on DPW’s Hayes Street project.

Last week

The contractor shifted crews to Hayes Street. Staff began working on installing concrete bus pads along Hayes Street. The contractor began working at the Steiner, Fillmore and Webster intersections. The bus pad work required the contractor saw-cut and remove the existing roadway and street base at bus stops. Crews then began installing reinforced rebar pads in the pits in order to back-fill them with fresh concrete.

The contractor also continued curb ramp work on Hayes at the Steiner, Scott, and Clayton intersections.

This Week (December 4-9)

Crews are scheduled to pour the bus pads at the Hayes/Steiner, Hayes/Fillmore, and Hayes/Webster intersections. Unfortunately, once the concrete has been poured, the area will be off-limits to vehicle traffic for 10 days to ensure the concrete reaches the necessary strength. During bus pad construction, the work will necessitate we temporarily relocate the bus stops. You may see some nearby areas posted for “No Parking 24/7” as they serve as temporary bus stops.

*** Please Note: The construction schedule is subject to change due to rain, equipment breakdown, unforeseen field conditions, etc. Please see the posted “no parking” barricades for exact parking restrictions. Parking restrictions may vary per block. ***

Project website:  www.sfpublicworks.org/haighthayes

 

, ,

D5 Construction Update – Meeting Thursday August 3, 2017

 

Supervisor Breed will be holding a community meeting on Thursday, August 3rd at 6:30 p.m. at 55 Fillmore Street (IBEW Meeting Hall). The departments responsible for the construction projects on Hayes and Haight streets will be in attendance (SF Public Works, SF Public Utility Commission, and SF Municipal Transportation Agency). We encourage you to come and voice your questions and concerns.

 

SFDPW Work for Week of July 4

Week of July 4, 2017

Crews are not scheduled to work on Monday July 3, 2017 and Tuesday July 4, 2017 in observance of Independence Day.

– The contractor will continue Auxiliary Water Supply System (AWSS) work at the Haight & Divisadero intersection.

– Sewer lateral replacement work will continue on Hayes Street between Buchanan and Webster streets. The sewer lateral work on this block is expected to take approximately one more week to complete.

– Curb ramp and bus pad work will continue at Hayes and Divisadero

Hayes Sewer, Water, and Paving Project Update 5/1/2017

On Tuesday April 18, 2017, the contractor began sewer main replacement work on Hayes Street between Laguna and Buchanan.

Week of May 8, 2017

–  Crews are scheduled to commence water main replacement work at the Haight & Scott streets intersection.

– The contractor will continue sewer main replacement work on Hayes Street between Laguna and Buchanan streets. The sewer work is tentatively scheduled to wrap up this week on the block. Crews will then commence sewer main replacement work on Hayes between Buchanan and Webster streets.

http://www.sfpublicworks.org/haight-hayes

 

,

City work around Alamo Square

SFMTA on McAllister

Bigger Buses for 5 Fulton Local Service

SFMTA is adding more of the bigger 60-foot trolley buses to provide more room for riders on 5 Fulton local and 5-Rapid service.  https://www.sfmta.com/projects-planning/projects/5-fulton-rapid-project

SFMTA’s plans for traffic lights and roundabouts for McAllister Street are going to be implemented this year as well. Neighbors spoke out against the proposals repeatedly at hearings.

What’s included in the proposal?

Traffic circles at McAllister and Steiner
Traffic lights at McAllister and Scott, McAllister and Broderick

Read the details:  https://www.sfmta.com/about-sfmta/blog/more-muni-forward-service-improvements-roll-out-february-25

These projects were approved in September 2015.

 

SFDPW on Hayes

Haight & Hayes Sewer, Water, and Paving Project

Week of April 17, 2017

The SFDPW contractor is scheduled to begin sewer main replacement work on Hayes Street between Laguna and Buchanan streets.

http://www.sfpublicworks.org/haight-hayes