DPW Sewer Project Update 10/24/16

This Week (10/24)

Crews will continue work on remaining sewer laterals. This work will occur on Haight Street near the intersection of Haight and Fillmore. The “no parking” barricades will be placed at locations where sewer lateral and/or culvert work is to be performed. This work will not impact sewer service.

On Scott Street, south of Hayes Street, the Contractor is expected to complete the installation of the sewer main, a drainage culvert and two manholes.

Week of October 31, 2016

The contractor will begin sewer main replacement on Hayes Street between Lyon and Central streets.

On Haight St, between Scott St. and Buchanan St., the contractor will begin sewer main trench restoration work. The sewer trench restoration work on Haight Street, Scott to Buchanan, is expected to take 2.5 weeks to complete barring any weather delays.

The water lateral connection work is tentatively scheduled to commence towards the middle of the week on the 1400 block of Haight Street.

*** Please Note:  The schedule may change due to rain in the forecast. Please see the posted “no parking” barricades for exact parking restrictions. Parking restrictions may vary per block. ***

Feel free to contact Alex Murillo if you have additional questions/concerns. Also, please invite your neighbors to visit our project page and sign-up for email updates. The DPW project page is www.sfpublicworks.org/haight-hayes. Thank you.

Alex M. Murillo
Public Affairs Officer

Office of Communications & Public Affairs | San Francisco Public Works | City and County of San Francisco
30 Van Ness Ave., 5th Floor | San Francisco, CA 94102 | W (415) 558-5296 | sfpublicworks.org · twitter.com/sfpublicworks

 

New Tree Planting in Progress

 

trees-for-future

Each of these roped-off squares will be planted with one of the trees bought by the Alamo Square Trees for Future Generations fundraiser! Thank you to all our donors and the Alamo Square Neighborhood Association!

Read more on Hoodline:

http://hoodline.com/2016/10/planting-for-50-donated-alamo-square-trees-breaks-ground

 

DPW Sewer Replacement Update 10/5/16

photo (3).JPG

This week (October 3-7)

The contractor has completed the sewer main replacement work on Hayes Street between Scott and Divisadero streets. This week, the contractor is replacing sewer laterals on the north side of this block.

Week of October 10, 2016

 

On Hayes Street, between Scott and Divisadero, the contractor will begin replacing sewer laterals on the south side of the block.

Week of October 17, 2016

The contractor will complete the sewer work on Hayes Street between Scott and Divisadero streets.   Sewer main replacement work is tentatively scheduled to commence on Hayes Street from Lyon to Central the week of October 24, 2016.

On Haight St, between Scott St. and Buchanan St., the contractor will begin sewer trench restoration work. The trench restoration work will begin at the Haight and Scott streets intersection and proceed in an easterly direction towards Buchanan Street. The contractor is anticipated to complete this phase of trench restoration work by the first week of November. The bus stops at Pierce, Fillmore and Buchanan will be temporarily relocated as work progresses along Haight Street. Bus stops will be relocated to mid-block locations. The “no parking” barricades will be placed at locations where trench restoration work is to be performed.

*** Please Note:  The schedule is subject to change due to rain, equipment breakdown, and/or unforeseen field conditions. Please see the posted “no parking” barricades for exact parking restrictions. Parking restrictions may vary per block. ***

For additional information on the project please visit www.sfpublicworks.org/haight-hayes. Also, please invite your neighbors to sign-up for email updates by adding themselves to the distribution list via the webpage. Thank you.

 

Alex M. Murillo

Public Affairs Officer

Office of Communications & Public Affairs  |  San Francisco Public Works  |  City and County of San Francisco

30 Van Ness Ave., 5th Floor  |  San Francisco, CA 94102  |  W (415) 558-5296  |  sfpublicworks.org ·twitter.com/sfpublicworks